Applying for a new power supply from GEPCO is now much easier than before. Rather than running around at different places and filling physical applications, one may now make his or her application from the comfort of his or her own house through an online portal for the Electricity New Connection (ENC).

Guide Focus: This comprehensive guide will cover all aspects related to the GEPCO new connection, which includes documents needed, how to make online applications, demand notice, connection charges, application status check and processing period.

What is a GEPCO New Connection?

GEPCO New Connection refers to the power connection service rendered by Gujranwala Electric Power Company Limited (GEPCO) for the residential or commercial property or any other building that falls within the coverage area of GEPCO.

💡 If you have newly built your house or set up any business but there is no power meter installed, you need a new connection.

Who Can Apply for a GEPCO New Connection?

One can apply for a new GEPCO connection if:

  • You own a residential house.
  • You own a commercial shop or office.
  • You are constructing a new building.
  • You need a new industrial or agricultural electricity connection.
  • You have all the required ownership documents.

Note: Both property owners and legally authorized applicants can apply, provided they submit the required documents.

Types of GEPCO Electricity Connections

GEPCO offers different types of electricity connections based on the purpose of use.

Connection Category Scope & Application
Residential Connection This connection is for houses, apartments and residential buildings.
Commercial Connection Commercial connections are provided for shops, offices, restaurants and other business premises.
Industrial Connection Industries and factories requiring electricity for manufacturing can apply for an industrial connection.
Agricultural Connection Farm owners can apply for agricultural connections to operate tube wells and other farming equipment.

Documents Required for a GEPCO New Connection

Before starting your application, keep the following documents ready:

  • Copy of the applicant's CNIC
  • Proof of property ownership
  • Copy of a utility bill of the nearby electricity connection (if necessary)
  • Registered phone number
  • Recent passport-size photograph (if requested)
  • Site plan or location map (where applicable)
  • Affidavit or additional documents if required by GEPCO

⚠️ Ensure that all papers are legible and valid to prevent any delay in the approval procedure.

How to Apply for a GEPCO New Connection Online

An "Electricity New Connection (ENC)" online system has been made available by the Government of Pakistan through which applicants may apply to any electricity distribution company, including GEPCO, in Pakistan.

Follow these steps:

Step 1: Open the ENC Portal

Visit the official Electricity New Connection (ENC) portal.

Step 2: Register Your Account

Register yourself by using your email address and mobile number if you are a new user.

Step 3: Complete the Application Form

Enter the following details:

  • Name of the applicant
  • CNIC number
  • Mobile number
  • Complete property address
  • Connection category
  • Required load

Please double-check all information before moving on to the next step.

Step 4: Upload the Required Documents

Upload the scanned version of the required documents in the specified format.

Step 5: Submit the Application

Go through the completed application and submit it. After submitting your application, you will get a reference number which you can use for checking the status of your application.

Offline Application

In case you are unable to apply online, you can also apply at your nearest GEPCO customer service center.

This would include:

  • Collecting the application form
  • Filling in the required information
  • Attaching all required documents
  • Submitting the application to the concerned office

GEPCO staff will verify your documents before processing your request.

What is a Demand Notice?

After your application and documents are verified, GEPCO issues a Demand Notice.

The Demand Notice contains:

  • Connection charges
  • Security deposit
  • Meter installation charges
  • Other applicable fees

Important: You must pay the Demand Notice within the specified time through the authorized bank. Keep the paid receipt safely because it may be required during the connection process.

GEPCO New Connection Charges

The total cost of a new connection depends on several factors, including:

  • Connection category
  • Required electricity load
  • Meter type
  • Distance from the existing electricity line
  • Taxes and fees applicable by the government

As the above mentioned taxes and fees may be subject to changes at any point in time, it is always wise to consult the latest Demand Notice applicable for your application.

How to Track Your GEPCO New Connection Application

Once you have made your application, you can follow its progress online very easily. All you need to do is provide your application reference number on the ENC website.

You may see statuses such as:

  1. Application Submitted
  2. Under Verification
  3. Demand Notice Issued
  4. Payment Received
  5. Meter Installation in Progress
  6. Connection Completed

It will allow you to keep yourself updated without going to the GEPCO office several times.

Timeline and Process Management

⏱️ Expected Processing Period 🚨 Common Causes of Delay
This is dependent upon the kind of connection applied for, document validation, technical assessment, and payment of the Demand Notice.

If everything is in place, then it should not take more than a few weeks. However, if it involves additional approvals or network expansion, then it will obviously take longer.
Some applications take longer due to:
  • Missing documents
  • Incorrect CNIC information
  • Incomplete application form
  • Unpaid Demand Notice
  • Issues Relating To Property Ownership
  • Delays due to technical/situation inspection
Accurate submission of the details can help cut down the process time drastically.

Steps to Speed Up the Process

Simply follow these steps to avoid any unnecessary delays:

  • Ensure accuracy of all personal information.
  • Upload clear and readable documents.
  • Use an active mobile number.
  • Pay the Demand Notice prior to its expiration.
  • Retain the application reference number.
  • Provide further information requested by GEPCO promptly.

Frequently Asked Questions

Is it possible to apply for a GEPCO new connection online?
Yes. You can do that via the official Electricity New Connection (ENC) portal.

Which documents are needed for this?
Usually, your CNIC, proof of property ownership, registered mobile number and other necessary documents depending upon the type of connection you seek.

How do I check my application status?
You can do it by using the reference number provided after submission of your application online.

How much time is required for a new connection?
The processing time depends upon the verification of documents, inspection and payment of Demand Notice. Usually, the process takes several weeks only if everything is in place.


A GEPCO new connection application has been simplified by the use of the online Electricity New Connection (ENC) portal. Do you need electricity in your house, shop, office or industrial unit? The online system will allow you to make your application, submit your documents, pay the Demand Notice and monitor your application without having to make any office visits.

📣 Remember: Provide accurate information, submit clear documents and pay your Demand Notice on time. By adhering to the right procedure, you will get your new electricity connection as fast as possible.