You paid your GEPCO demand notice on time. Months later, a second letter arrives. It says material rates have gone up and asks for more money before GEPCO finishes the work. This is the "additional" or "revised" demand notice.

Is it fair? NEPRA has answered that in many GEPCO complaints. The answer comes down to three tests, and two of them are about dates.

The three tests in one look

  1. Is your connection a home up to 20 kW or a shop up to 15 kW? If yes, no escalation can be charged at all.
  2. What was GEPCO's deadline? Count from the day you paid the first notice in full.
  3. When did the rates go up? Before the deadline, you may have to pay the difference. After it, you should not.

Test 1: Is your load small enough to be exempt?

NEPRA's Consumer Service Manual (CSM) 2025 has a clear line on this. No escalation cost shall be charged to residential consumers up to 20 kW load. The same applies to commercial consumers up to 15 kW load.

So an ordinary house or small shop in Gujranwala, Sialkot or Gujrat should not get an escalation notice. Industrial connections, tube wells, bigger loads and housing schemes are not exempt. For them, tests 2 and 3 decide.

Test 2: When should GEPCO have finished?

Annexure-III of the CSM sets a time frame for every load band. NEPRA counts the deadline from the date you paid the demand notice in full. It adds the days for issuing material, doing the work and installing the meter.

Load applied forDays after full payment
Up to 15 kW (400 V)20 days
Above 15 kW up to 70 kW (400 V)34 days
Above 70 kW up to 500 kW (400 V)46 days
Above 500 kW up to 5,000 kW (11 kV or 33 kV)76 days
66 kV and above451 days

Example: you paid a 22 kW industrial notice on 28 April. The deadline is 34 days later, on 1 June. NEPRA used exactly this count in a Gujrat case below.

If GEPCO misses the deadline, the CSM says it must give reasons for each day of delay in writing to you, with a copy to NEPRA. A delay does not cancel GEPCO's duty to connect you.

Test 3: Did the rates rise inside or outside that window?

This is the core rule. NEPRA's decisions quote it as clause 2.4.6 of the CSM:

  • Rates rose within the time allowed for your connection: you pay the extra cost.
  • Rates rose after that time ran out: no escalation charges apply.
  • Material already taken from the store and fitted: NEPRA has not allowed new rates on it.

If GEPCO is short of material, CSM clause 2.7.1 lets it ask you to buy the material from its approved vendors. GEPCO then charges 2.5% of the material cost for inspection and 8% for installation. In several cases below, GEPCO never sent such a letter, and NEPRA held that against it.

Seven GEPCO cases NEPRA has decided

All of these are on NEPRA's GEPCO decisions page. Amounts are as written in the decisions.

Case (decision date)LoadGEPCO's deadlineExtra askedResult
Canal Valley, Daska (Nov 2022)415 kW22 Nov 2021Rs 3,378,000Payable: rates rose on 1 Nov 2021, inside the window
Industrial, Kunjah, Gujrat (Aug 2023)22 kW1 Jun 2021Rs 188,500Cut down to rates of 13 Oct 2021
Ramzan Town Ext., Daska (Oct 2023)662 kW12 Oct 2022Rs 2,955,680Withdrawn and refunded; only two transformers re-priced
Industrial, Khonan Gharbi, Gujrat (Feb 2024)18 kW28 Jul 2021Rs 115,363Withdrawn; any excess refunded or adjusted in bills
Al-Raheem Residentia, Narowal (Jan 2026)798.33 kW25 Apr 2021Rs 8,916,335, later Rs 6,348,000Withdrawn; only rates of 25 Apr 2021 allowed
Siddiqui Housing Scheme, Daska (Jan 2026)786 kW27 May 2022Rs 4,674,075Re-priced at rates of 27 May 2022
Garden Town Phase-III, Gujranwala (May 2026)14,726 kW26 May 2023Rs 119,439,110Payable, but not on material already installed

When GEPCO was right

In Canal Valley, the sponsor paid on 7 October 2021. GEPCO revised its material rates from 1 November 2021. That was inside the 46-day window. NEPRA said the extra amount was payable.

"...the Complainant is not liable to pay the difference of capital cost if enhancement in material cost occurred after forty six (46) days of payment of first demand notice in full."

NEPRA decision, Canal Valley vs GEPCO, November 2022

Garden Town Phase-III is similar. Its window was 451 days, so the April 2023 rates fell inside it. But NEPRA still said GEPCO could not re-price material that was already fitted at site.

When GEPCO was late

The two small industrial cases in Gujrat matter most for ordinary applicants. Both had a 34-day window. In both, GEPCO connected months late and then sent a second notice for the transformer's new price.

In the Khonan Gharbi case, the applicant had already paid the second notice under protest. NEPRA still told GEPCO to withdraw it and refund or adjust any excess in future bills. GEPCO had not asked the applicant to buy the missing material, and had not given written reasons for the delay.

In the Kunjah case, GEPCO blamed a Covid-19 transformer shortage. NEPRA accepted that supply was disturbed until 13 October 2021 and allowed rates only up to that date. Even after that, GEPCO took more than three months to connect.

When GEPCO blamed the applicant

In the Siddiqui Housing Scheme case, GEPCO said the work stopped because of a right-of-way problem. NEPRA found the problem was only about poles outside the society. Nothing stopped GEPCO from fitting the transformers inside, and NEPRA called the excuse a cover for negligence. A July 2026 corrigendum fixed the rate date at 27 May 2022, which is 76 days after the 12 March 2022 payment.

GEPCO also points to the small print in its demand notices and approval letters. One line says any excess expenditure "for any reason" is payable by the sponsor. In Garden Town and Canal Valley, NEPRA said this reading goes against the CSM. The manual's rule comes first.

What to do when the letter arrives

  1. Find your payment date. Use the bank receipt of the first notice, not the notice's issue date.
  2. Work out the deadline. Use your load band from the table above.
  3. Ask for the details in writing. For cost deposit cases, CSM clause 2.4.10 says GEPCO must give you the full estimate and bill of quantities with the notice. Ask which month's rate list was used and which items were re-priced.
  4. Compare the dates. Did the new rates start before or after your deadline? Were items already fitted re-priced?
  5. Complain to GEPCO first. Write to the office that issued the notice (numbers are in our GEPCO telephone directory). Keep copies.
  6. Then go to NEPRA. If GEPCO does not fix it, file on the NEPRA complaint system. Attach both notices, both receipts and your dates.

Do not miss the due date while you argue. A demand notice gives 30 days to pay. You can ask for a 30-day grace period, but you must submit the request at least three days before the notice expires (CSM 2.4.3). If you pay in installments, any rate rise during that period is yours to bear (CSM 2.4.7).

Once the connection is on, try our GEPCO monthly bill estimator to plan the running cost, and use the GEPCO bill page to check your first bill.

Questions readers ask

Can GEPCO send an additional notice for a normal house?

Not for escalation if the load is up to 20 kW. The CSM exempts homes up to 20 kW and shops up to 15 kW.

I already paid the extra amount. Is it too late?

Not always. In two GEPCO cases the applicant had paid, and NEPRA still ordered a refund or bill adjustment.

From which date is the deadline counted?

From the date the first demand notice was paid in full.

Does a material shortage let GEPCO charge new rates?

Not by itself. The CSM lets GEPCO ask you to buy the material from its approved vendors. NEPRA has looked for that letter in these cases.

Can GEPCO re-price material it already installed?

NEPRA said no in the Ramzan Town and Garden Town cases. Only pending items were re-priced.

Sources: NEPRA Consumer Service Manual 2025 (GEPCO copy), clauses 2.4.3, 2.4.6, 2.4.7, 2.4.10, 2.7.1 and Annexure-III; NEPRA Authority decisions on GEPCO complaints, including the Garden Town decision of 5 May 2026 and the Khonan Gharbi decision of February 2024.